Aurelia Metals has received a Notice of Determination from Cobar Shire Council approving an increase in the Peak processing plant throughput rate from approximately 800ktpa to 1.2Mtpa.

The development consent is the final regulatory approval required to operate the Peak processing plant at the expanded rate. This higher operating capacity is enabled by the Tailings & Water Management Project, Tertiary Ball Mill Project, and Crushing & Materials Handling Expansion Project.

"The receipt of this development consent is an important milestone, aligning the approved processing capacity with our growth plans to increase mining and processing rates across our Cobar Basin operations."

“The process plant expansion is already well advanced, with the new tailings thickener commissioned in June 2026. The Tertiary Ball Mill Project is progressing to schedule, with commissioning expected in Q1 FY27, while planning for the Crushing and Materials Handling Expansion Project continues in line with the broader mine ramp-up.”
— Martin Cummings, Interim Chief Executive Officer

Aurelia operates three underground base metal mines across its Peak and Federation operations in western New South Wales. In addition to these producing assets, the company is progressing the Great Cobar Project, a consented high-grade copper development located at Peak, with first ore production scheduled for fiscal 2028.

Commissioning of the Tertiary Ball Mill Project at Peak is expected in the first quarter of fiscal 2027.