Legacy Minerals Progresses Mt Carrington Scoping Study on Expanded 47.9Mt Resource

By Mining Hub News Desk
6 September 2026, 8:50 p.m. EDT 2 min read

Legacy Minerals Holdings Ltd has advanced an Optimised Scoping Study for its flagship Mt Carrington Gold-Silver Project in New South Wales, targeting plant throughput options above the original 1 million tonnes per annum baseline.

The current evaluation marks a shift from the May 2026 Scoping Study, which was underpinned by a production target of 10.1 million tonnes. The updated study incorporates a July 2026 Mineral Resource Estimate that increases total resource tonnes by 39% to 47.9 million tonnes at 1.0 grams per tonne gold equivalent, containing 714,000 ounces of gold and 35 million ounces of silver.

Total resource tonnage at the project has expanded by 151% since the initial acquisition by Legacy Minerals.

“While the May 2026 Scoping Study confirmed a simple, low-capex development pathway at a 1Mtpa scale, it was underpinned by a Production Target of just 10.1Mt, drawn from a Mineral Resource that has since grown to 47.9Mt.” — Christopher Byrne, CEO & Managing Director

Indicated Resources have increased by 69% to 19.3 million tonnes at 1.22 grams per tonne gold equivalent, compared to 11.4 million tonnes in the 2025 estimate. The processing strategy remains unchanged, utilising a cyanide-free flotation flowsheet to produce a saleable precious metal concentrate.

Ausenco Services Pty Ltd is undertaking process engineering, cost estimating and financial modelling for the study, while WSP Australia Pty Limited handles mine optimisations and mine scheduling.

“With Resource tonnes up by 39%, silver ounces up by 44%, and Indicated Resources up by 69% to 19.3Mt, we now have the opportunity to assess the scale economies of a larger plant and an expanded Production Target, with the aim of increasing annual metal production, extending cash flow and improving Project economics.” — Christopher Byrne, CEO & Managing Director

Legacy Minerals expects to release the results of the Optimised Scoping Study in the December 2026 quarter.

Read the full announcement: Optimised Scoping Study Progressing Well at Mt Carrington