Measured And Indicated Resources Rise 27% As Salazar Files El Domo Technical Report

By Mining Hub News Desk
13 August 2026, 6:53 p.m. EDT 1 min read

Salazar Resources Limited has filed an independent National Instrument 43-101 technical report for the El Domo-Curipamba polymetallic project in Ecuador's Bolívar and Los Ríos provinces, formalising resource updates and operational plans previously disclosed to the market.

Prepared by SRK Consulting (China) Ltd. for project operator Silvercorp Metals Inc., the report carries an effective date of December 31, 2025, and was issued on May 31, 2026. Salazar holds a 25% carried interest in the asset, while Silvercorp owns the remaining 75% and acts as operator.

The technical report supports the updated mineral resource and reserve figures announced in July 2026. Measured and indicated mineral resources increased by 27%, rising from 9 million tonnes to 11.4 million tonnes compared to earlier estimates.

Construction is underway at the project under Silvercorp's operatorship, with production of the first commercial concentrates expected to begin in mid-2027.

Read the full announcement: Salazar Resources Files NI 43-101 Technical Report for the Curipamba-El Domo Project